GMAT Question of the Day: GMAT Work Problems
5 painters, each working at the same rate, together can paint a certain fence in 25 days. By what percent must the rate of each painter increase so that they can complete the job in ten days?
A. 125%
B. 150%
C. 200%
D. 250%
E. 275%
Answer: B